“Plaintiff claims that Defendant provided plans and specifications for the project that were not correct. To establish this claim, Plaintiff must prove all of the following: 1. That Defendant provided Plaintiff with plans and specifications for Defendant’s project; 2. That Plaintiff was required to follow the plans and specifications provided by Defendant in bidding on/constructing the project; 3. That Plaintiff reasonably relied on the plans and specifications for the project; 4. That the plans and/or specifications provided by Defendant were not correct; and 5. That Plaintiff was harmed because the plans or specifications were not correct.”
[CACI Jury Instructions [citations omitted]]