“Plaintiff claims that Defendant breached the parties’ contract by delaying/accelerating Plaintiff’s work, causing
Plaintiff harm. If you find that Defendant delayed/accelerated the work, you may award damages to Plaintiff for all harm caused by the delay/acceleration, including the following: 1. Expenditures that Plaintiff made for labor, services, equipment, or materials that she otherwise would not have made but for the delay/acceleration; 2. Overhead that Plaintiff otherwise would not have incurred but for the delay/acceleration; and 3. Increase in the cost of labor, services, equipment, or materials already required under the contract that resulted from the delay/acceleration.”

[CACI Jury Instructions [citations omitted]]